Baglihar Hydropower Project Latest News
Operations were suspended at the 450 MW stage 1 Baglihar hydropower project on the Chenab river in Jammu and Kashmir after it got flooded recently.
About Baglihar Hydropower Project
- It is a 900 MW run-of-the-river power project on the Chenab River in the Ramban district of Jammu and Kashmir.
- It consists of a concrete gravity dam 144.5 m high and 363 m long, which has a total volume of 1.9 million m³, creating a reservoir with a capacity of 475 million m³.
- The underground powerhouse is 221 m long, 24 m wide, and 51 m high.Â
- The project consists of two stages of 450 MW each.
- The project construction commenced in 1999 and subsequently entered into commercial operation in 2008.
Key Facts about Chenab River
- It is the largest of the five tributaries of the Indus River.
- Course:
- Origin: It is formed by the confluence of two streams, Chandra and Bhaga, in the Lahaul and Spiti Districts of Himachal Pradesh.
- In its upper reaches, it is also known as the Chandrabhaga.
- It flows through the Jammu and Kashmir union territory, Himachal Pradesh, and after receiving the Jhelum River near Trimmu, the Chenab empties into the Sutlej River.
- Total Length: 974 kilometers
- The Chenab valley is a structural trough formed by the great Himalayan and Pir Panjal ranges.
- Major Tributaries:
- Left Bank: Niru, Tawi, Neeru, and Liddrari.
- Right Bank: Ans, Bhut Nalla, Bichleri, Kalnai Marusudar, and Miyar Nalla.
- Major Dams on Chenab River: Salal (rockfill dam), Aalal (concrete dam), Baglihar, and Dul.
Source: TOI
Last updated on August, 2026
→ UPSC Mains 2026 will be conducted on 21st, 22nd, 23rd, 29th and 30th August 2026.
→ Check out the latest UPSC Syllabus 2026 here.
→ UPSC Mains Admit Card 2026 is expected to be released in early August at upsc.gov.in or upsconline.nic.in
→ Enroll in Vajiram & Ravi’s UPSC Mains Test Series 2026 for structured answer writing practice, expert evaluation, and exam-oriented feedback.
→ Go through the UPSC Mains Previous Year Papers to enhance your preparation.
→ Download UPSC Mains Essay Paper 2025, UPSC Mains GS Paper-I 2025, UPSC Mains GS Paper-II 2025, UPSC Mains GS Paper-III 2025, UPSC Mains GS Paper-IV 2025, UPSC Mains English (Compulsory) Paper 2025, UPSC Mains Hindi (Qualifying) Paper 2025 here.
→ UPSC has released UPSC Toppers List 2025 with the Civil Services final result on its official website.
→ UPSC Calendar 2027 has been released.
→ Also check Best UPSC Coaching in India
Baglihar Hydropower Project FAQs
Q1. On which river is the Baglihar Hydropower Project located?+
Q2. What is the total installed capacity of the Baglihar Hydropower Project?+
Q3. What type of hydropower project is Baglihar?+
Q4. What type of dam has been constructed under the Baglihar Project?+
Tags: baglihar hydropower project prelims pointers upsc current affairs upsc prelims current affairs