Kiru Hydroelectric Project

Kiru Hydroelectric Project is a 624-megawatt (MW) run-of-river project being developed over the Chenab River. Read more about Kiru Hydroelectric Project, Location, Capacity, Latest News.

Kiru Hydroelectric Project

Kiru Hydroelectric Project Latest News

The 624-megawatt Kiru hydroelectric project recently reached a significant milestone with the completion of 10 lakh cubic meters of Dam Concreting, out of a total target of 12 lakh cubic meters.

About Kiru Hydroelectric Project

  • It is a 624-megawatt (MW) run-of-river project being developed over the Chenab River near the villages of Patharnakki and Kiru in Kishtwar District, Jammu and Kashmir (J&K).
  • It is located between the Kirthai II hydroelectric project to its upstream and the Kwar hydroelectric project to its downstream.
  • The project will include the construction of a concrete gravity dam with a height of 135 m and an underground powerhouse located on the left bank of the river that will comprise four vertical Francis turbines with a capacity of 156 MW each. 
  • The project will provide much-needed power for the grid in northern India. 
  • It is being developed by Chenab Valley Power Projects (CVPP), a joint venture between 
    • National Hydroelectric Power Corporation (NHPC, 49%)
    • Jammu & Kashmir State Power Development Corporation (JKSPDC, 49%) 
    • Power Trading Corporation (PTC, 2%).

Source: STATES

Latest UPSC Exam 2026 Updates

Last updated on January, 2026

→ Check out the latest UPSC Syllabus 2026 here.

→ Join Vajiram & Ravi’s Interview Guidance Programme for expert help to crack your final UPSC stage.

UPSC Mains Result 2025 is now out.

UPSC Notification 2026 is scheduled to be released on January 14, 2026.

UPSC Calendar 2026 has been released.

UPSC Prelims 2026 will be conducted on 24th May, 2026 & UPSC Mains 2026 will be conducted on 21st August 2026.

→ The UPSC Selection Process is of 3 stages-Prelims, Mains and Interview.

→ Prepare effectively with Vajiram & Ravi’s UPSC Prelims Test Series 2026 featuring full-length mock tests, detailed solutions, and performance analysis.

→ Enroll in Vajiram & Ravi’s UPSC Mains Test Series 2026 for structured answer writing practice, expert evaluation, and exam-oriented feedback.

→ Join Vajiram & Ravi’s Best UPSC Mentorship Program for personalized guidance, strategy planning, and one-to-one support from experienced mentors.

UPSC Result 2024 is released with latest UPSC Marksheet 2024. Check Now!

UPSC Toppers List 2024 is released now. Shakti Dubey is UPSC AIR 1 2024 Topper.

→ Also check Best UPSC Coaching in India

Kiru Hydroelectric Project FAQs

Q1. Where is the Kiru Hydroelectric Project located?+

Q2. Over which river is the Kiru Hydroelectric Project being developed?+

Q3. What is the total installed capacity of the Kiru Hydroelectric Project?+

Q4. The Kiru Hydroelectric Project is classified as which type of hydro project?+

Tags: kiru hydroelectric project

Vajiram Content Team
Vajiram Content Team
UPSC GS Course 2026
UPSC GS Course 2026
₹1,75,000
Enroll Now
GS Foundation Course 2 Yrs
GS Foundation Course 2 Yrs
₹2,45,000
Enroll Now
UPSC Mentorship Program
UPSC Mentorship Program
₹85000
Enroll Now
UPSC Sureshot Mains Test Series
UPSC Sureshot Mains Test Series
₹19000
Enroll Now
Prelims Powerup Test Series
Prelims Powerup Test Series
₹8500
Enroll Now
Enquire Now