Hybrid Annuity Model (HAM) is a public-private partnership (PPP) framework introduced by the Government of India to enhance infrastructure development, particularly in the road sector. HAM amalgamates the strengths of two prevalent models: Engineering, Procurement, and Construction (EPC) and Build, Operate, Transfer (BOT).
Under Hybrid Annuity Model, the government contributes 40% of the project cost during the construction phase, while the private developer finances the remaining 60%. This model aims to balance risk-sharing between the public and private sectors, ensuring efficient project execution and long-term sustainability.
Hybrid Annuity Model Meaning
Hybrid Annuity Model (HAM) is a Public-Private Partnership (PPP) framework introduced by India’s National Highways Authority of India (NHAI) in January 2016. It combines elements of the Engineering, Procurement, and Construction (EPC) and Build-Operate-Transfer (BOT) models to balance risk and investment between the government and private developers.
EPC (Engineering, Procurement, and Construction)
The EPC model—short for Engineering, Procurement, and Construction—is a project execution method where the government hires private companies to build infrastructure, such as roads. Once the construction is finished, the private contractors have no further obligations. They do not own the asset, manage toll collection, or handle its maintenance—those responsibilities remain entirely with the government.
BOT (Build, Operate, Transfer)
Build-Operate-Transfer (BOT) model is a public-private partnership framework where private entities are engaged in the construction, operation, and maintenance of infrastructure, such as roads, for a fixed duration, typically ranging from 10 to 15 years.
- During this concession period, the private party is responsible for arranging project financing. After the agreed term ends, ownership of the infrastructure is transferred back to the government.
- In return for their investment and upkeep, the private firms are compensated through regular payments known as annuities. This payment mechanism is commonly referred to as the BOT-Annuity model.
Hybrid Annuity Model Working
Hybrid Annuity Model Working is based on a public-private partnership framework where the government provides financial support to a private developer (concessionaire) through scheduled annuity payments over a defined concession period, typically ranging from 15 to 20 years.
- These annuity payments are carefully calculated to cover the developer's project expenses, ensuring cost recovery and a reasonable return on investment.
- Under HAM, the private developer is responsible for designing, constructing, financing, and maintaining the infrastructure project during the concession period.
- In HAM, the project cost is shared between the government and the private developer in a 40:60 ratio.
- The risk is shared between the government and the private developer, with the latter managing construction and maintenance while the government assumes financial risk.
- Upon the completion of the concession period, ownership of the project reverts to the government.
- This model balances risk-sharing and provides a stable revenue stream to developers, making it an attractive option for infrastructure projects in sectors like roads and highways.
Hybrid Annuity Model Features
Hybrid Annuity Model Features include a transparent bidding process with Life Cycle Cost as the key parameter, government responsibility for toll collection, and concessionaire accountability for project maintenance throughout the concession period.
- Bidding Process: The Hybrid Annuity Model (HAM) ensures transparency by selecting the concessionaire through a competitive bidding process, where the Life Cycle Cost is the primary criterion for selection.
- Concessionaire Role: The concessionaire is obligated to maintain the project throughout the entire concession period, which includes the time required for construction as well as a set 15-year period for operational activities.
- Toll Collection: Toll collection responsibilities under HAM lie with the government, insulating the private developer from traffic and revenue risks, ensuring stable cash flow for the concessionaire.
- Risk Sharing: HAM balances risk between the government and private developers. The government assumes revenue risk, while the developer handles construction and maintenance risks.
- Payment Structure: The government pays 40% of the project cost during construction and the remaining 60% as annuity payments over the concession period.
- Combination of EPC and BOT Models: HAM adopts a partnership approach by blending features of EPC and BOT models, effectively utilizing the strengths of both the public and private sectors to achieve efficient infrastructure development.
Hybrid Annuity Model Importance
Hybrid Annuity Model (HAM) balances risk between the government and private sector, ensuring timely project completion, enhancing private investment, and maintaining quality infrastructure by providing assured payments during the operational phase.
- Enhanced Private Participation: Unlike the BOT model, HAM has successfully attracted private investors by reducing their financial burden, as the government shares a significant portion of the project cost.
- Balanced Risk Distribution: HAM effectively distributes project risks between the government and private developers, ensuring a balanced and secure investment environment.
- Reduced Revenue Risk: Developers are safeguarded from revenue uncertainty due to the annuity-based payment system, eliminating concerns over traffic volumes and toll collection.
- Improved Infrastructure Development: By promoting the timely initiation and completion of road projects, HAM enhances road quality, reduces congestion, and ensures smoother travel for commuters.
Government Control over Revenue: The government retains control over toll collection, maintaining consistent revenue streams while developers focus on construction and maintenance.
Last updated on November, 2025
→ Check out the latest UPSC Syllabus 2026 here.
→ Join Vajiram & Ravi’s Interview Guidance Programme for expert help to crack your final UPSC stage.
→ UPSC Mains Result 2025 is now out.
→ UPSC Notification 2026 is scheduled to be released on January 14, 2026.
→ UPSC Calendar 2026 is released on 15th May, 2025.
→ The UPSC Vacancy 2025 were released 1129, out of which 979 were for UPSC CSE and remaining 150 are for UPSC IFoS.
→ UPSC Prelims 2026 will be conducted on 24th May, 2026 & UPSC Mains 2026 will be conducted on 21st August 2026.
→ The UPSC Selection Process is of 3 stages-Prelims, Mains and Interview.
→ UPSC Result 2024 is released with latest UPSC Marksheet 2024. Check Now!
→ UPSC Prelims Result 2025 is out now for the CSE held on 25 May 2025.
→ UPSC Toppers List 2024 is released now. Shakti Dubey is UPSC AIR 1 2024 Topper.
→ UPSC Prelims Question Paper 2025 and Unofficial Prelims Answer Key 2025 are available now.
→ UPSC Mains Question Paper 2025 is out for Essay, GS 1, 2, 3 & GS 4.
→ UPSC Mains Indian Language Question Paper 2025 is now out.
→ UPSC Mains Optional Question Paper 2025 is now out.
→ Also check Best IAS Coaching in Delhi
Hybrid Annuity Model FAQs
Q1. What is a hybrid annuity model?+
Q2. What is a hybrid annuity?+
Q3. What is EPC and HAM?+
Q4. What is the hybrid model of PPP?+
Q5. What is a hybrid model example?+