Kiru Hydroelectric Power Project

Kiru Hydroelectric Project is a 624-megawatt (MW) run-of-river project being developed over the Chenab River. Read more about Kiru Hydroelectric Project, Location, Capacity, Latest News.

Kiru Hydroelectric Power Project
Table of Contents

Kiru Hydroelectric Power Project Latest News

The Kiru Hydroelectric Power Project in Kishtwar district of Chenab Valley has entered the final phase of construction, with the latest monitoring report of the Centre showing that more than 83 percent of the work has been completed.

About Kiru Hydroelectric Power Project

  • It is a 624 MW run-of-the-river scheme being developed over the Chenab River in Kishtwar District of Jammu and Kashmir (J&K).
  • It is located between the Kirthai II hydroelectric project upstream and the Kwar hydroelectric project downstream.
  • The project will include the construction of a concrete gravity dam with a height of 135 m and an underground powerhouse located on the left bank of the river that will comprise four vertical Francis turbines with a capacity of 156 MW each.
  • The project is being developed by Chenab Valley Power Projects (CVPP), a joint venture between National Hydroelectric Power Corporation (NHPC, 49%), Jammu & Kashmir State Power Development Corporation (JKSPDC, 49%), and Power Trading Corporation (PTC, 2%). 
  • The project shall provide much-needed power in the northern grid and shall accelerate the process of development of remote areas of J&K. 

News: GK

Update Icon
Latest UPSC Exam 2026 Updates

Date IconLast updated on June, 2026

UPSC Prelims Result 2026 is now out.

UPSC IFoS Prelims Result 2026 is now out.

→ Enroll in Vajiram & Ravi’s UPSC Mains Test Series 2026 for structured answer writing practice, expert evaluation, and exam-oriented feedback.

→ Join Vajiram & Ravi’s UPSC Mentorship Program 2026 for personalized guidance, strategy planning, and one-to-one support from experienced mentors.

→ Join Vajiram & Ravi’s UPSC Mentorship Program 2027 for personalized guidance, strategy planning, and one-to-one support from experienced mentors.

UPSC Prelims Provisional Answer Key 2026 out for GS Paper 1 and CSAT.

UPSC Prelims Question Paper 2026 Out, Download GS Paper 1 PDF conducted on 24th May 2026.

UPSC Mains 2026 will be conducted from 21st August 2026 onwards, and UPSC Prelims 2027 will be held on 23rd May 2027.

UPSC Final Result 2025 is now out.

→ UPSC has released UPSC Toppers List 2025 with the Civil Services final result on its official website.

Anuj Agnihotri secured AIR 1 in the UPSC Civil Services Examination 2025.

UPSC Notification 2026 & UPSC IFoS Notification 2026 is now out on the official website at upsconline.nic.in.

UPSC Calendar 2027 has been released.

→ Check out the latest UPSC Syllabus 2026 here.

→ The UPSC Selection Process is of 3 stages-Prelims, Mains and Interview.

Shakti Dubey secures AIR 1 in UPSC CSE Exam 2024.

→ Also check Best UPSC Coaching in India

Kiru Hydroelectric Power Project FAQ's

Q1. What is the installed capacity of the Kiru Hydroelectric Power Project?+

Q2. On which river is the Kiru Hydroelectric Power Project being developed?+

Q3. What type of dam will be constructed under the Kiru Hydroelectric Power Project?+

Q4. Which company is developing the Kiru Hydroelectric Power Project?+

Tags: kiru hydroelectric power project

Vajiram Content Team
Vajiram Content Team
UPSC GS Course 2026
UPSC GS Course 2026
₹1,80,000
Enroll Now
GS Foundation Course 2 Yrs
GS Foundation Course 2 Yrs
₹2,45,000
Enroll Now
UPSC Mentorship Program
UPSC Mentorship Program
₹85000
Enroll Now
UPSC Sureshot Mains Test Series
UPSC Sureshot Mains Test Series
₹19000
Enroll Now
Prelims Powerup Test Series
Prelims Powerup Test Series
₹14000
Enroll Now
Enquire Now