About Barh Super Thermal Power Project (STPP):
- STPP is a 3.3GW supercritical coal-fired power station being developed by India’s state-owned National Thermal Power Corporation (NTPC) in Barh, Bihar.
- The power plant will house a total of five coal-fired power generating units of 660MW capacity each.
- The mega power project is being developed in two stages, with stage one comprising three units for a total installed capacity of 1,980MW and stage two involving two units for a total capacity of 1,320MW.
- The plant utilizes supercritical pressure technology to obtain improved thermal efficiency while reducing greenhouse gas emissions.
- Source of water: Barh town is located closer to the River Ganga which is the source of water for the coal-fired thermal power facility.
- Source of Coal:
- The coal required for stage one operation of the project will be procured from the Central Coal Fields, a subsidiary of India’s state-owned Coal India Limited (CIL).
- Coal for the stage two operations comes from the NTPC Chatti-Bariatu coal mine located in Jharkhand.
What is Supercritical pressure technology?
- Supercritical (SC) and ultra-supercritical (USC) power plants operate at temperatures and pressures above the critical point of water, i.e. above the temperature and pressure at which the liquid and gas phases of water coexist in equilibrium, at which point there is no difference between water gas and liquid water.
- This results in higher efficiencies – above 45%.
- SC and ultra -supercritical USC power plants require less coal per megawatt-hour, leading to lower emissions (including carbon dioxide and mercury), higher efficiency and lower fuel costs per megawatt.
Q1) What is the National Thermal Power Corporation (NTPC) Ltd?
NTPC Limited, formerly known as National Thermal Power Corporation, is an Indian central Public Sector Undertaking under the ownership of the Ministry of Power, Government of India which is engaged in generation of electricity and allied activities. It is India’s largest power utility with an installed capacity of 72,304 MW (including JVs), plans to become a 130 GW company by 2032.
Source: NTPC commissions 600 MW unit of Barh Super Thermal Power Project in Bihar
Last updated on June, 2025
→ UPSC Notification 2025 was released on 22nd January 2025.
→ UPSC Prelims Result 2025 is out now for the CSE held on 25 May 2025.
→ UPSC Prelims Question Paper 2025 and Unofficial Prelims Answer Key 2025 are available now.
→ UPSC Calendar 2026 is released on 15th May, 2025.
→ The UPSC Vacancy 2025 were released 1129, out of which 979 were for UPSC CSE and remaining 150 are for UPSC IFoS.
→ UPSC Mains 2025 will be conducted on 22nd August 2025.
→ UPSC Prelims 2026 will be conducted on 24th May, 2026 & UPSC Mains 2026 will be conducted on 21st August 2026.
→ The UPSC Selection Process is of 3 stages-Prelims, Mains and Interview.
→ UPSC Result 2024 is released with latest UPSC Marksheet 2024. Check Now!
→ UPSC Toppers List 2024 is released now. Shakti Dubey is UPSC AIR 1 2024 Topper.
→ Also check Best IAS Coaching in Delhi